More Digging

looking to King St.jpg

looking to train.jpg

inclinator.jpg

Excavation on the eastern side is completed with all shockcreting and anchoring done. Struts are in place on north west corner. Sewer along southern western boundary has been replaced. Inclinometers stable (monitoring movements of slopes and excavations - yellow pipe protruding from capping beam). 

Continuing work on bulk excavation. Will shortly commence pad footings for remaining struts along northern boundary.